Werk-Stadt

Halle 6

Werk-Stadt, Hall 6


ABB STRIEBEL & JOHN GmbH


Topic: Fast electrical installation in practice - perfect solutions from a single source


Tasks: 1. Install and connect the selective main circuit breaker S750 and surge protection OVR ZP in the new ComfortLine meter panel in the access.

2. Install selected DIN rail devices in the UK600 circuit distributor, equip them with the appropriate phase rails and connect them.

3. Convenient connection of Busch-flexTronics® thanks to the enlarged connection space.

4. Simply put Busch-flexTronics® into operation and control functions on the switching device or with your smartphone/tablet.

5. Pair the smartphone with the Busch-Radio BTconnect DAB and stream music from the smartphone to the radio and play it there. Pair the Busch-Radio BTconnect DAB with a BT speaker and play a radio station from the radio on the BT speaker.

6. Installing and connecting the module components of the individual Busch-Welcome® door outdoor station for 2-wire.

7. Configuration of the Busch-Welcome® door communication: Creating a project for a single-family home. Creating a project with the Smart Home Configurator for a 2-room apartment.

8. Fast and easy installation with SmissLine TP compared to classic DIN rail mounted devices in an existing electrical distribution system.


Performance level: 1st-3rd year of apprenticeship


Stand: W80


ABL GmbH


Topic: The perfect connection - SCHUKO high-tech plugs and couplings


Tasks: Making a SCHUKO extension cable


Performance level: 1st year of apprenticeship


Stand: W34


Albrecht Jung GmbH & Co.KG


Topic: JUNG HOME


Tasks: Installation & commissioning of the new Jung Home System


Stand: W82




Bals Elektrotechnik GmbH & Co.KG


Topic: Installation of a CEE connector 16A 5-pin with maintenance-free connection technology


Tasks: Stripping conductors,

Open the plug, pull in the cable, connect the conductors L1, L2, L3, N and PE. Screw the strain relief tight, test


Performance level: 1st year of apprenticeship


Stand: W62


BBC Cellpack GmbH


Topic: Installation of cable fittings in various low-voltage technologies


Tasks: Choice of: gel, connection, shrink technology, self-guided assembly, tools, cables, products are available


Performance level: 1st year of apprenticeship


Stand: W02


Federal Technology Center for Electrical and Information Technology


Topic: Experiencing e-mobility and e-norms differently


Tasks: The participant has the opportunity to drive the Carrera track on our stand. He is given the following task beforehand: Calculate the speed / kmh of the vehicle for one lap.


Performance level: 1st year of apprenticeship


Stand: W18


Cimco


Topic: Can you get the solar panel to work?


Tasks: Installation of a solar module with appropriate charging control. The focus of this application is on the MC4 plug connections that are used in almost all solar systems. To set up a plug connection, the correct use of a cable cutter, a stripping tool and a crimping tool is required. If all work is carried out correctly, the solar panel will work!


Performance level: 1st year of apprenticeship

Stand: W78



Gossen Metrawatt GmbH


Topic: VDE tests according to VDE 0100-600 and VDE 0701-0702


Tasks: Testing of mobile equipment, testing of fixed electrical installations


Performance level: 1st-3rd year of apprenticeship


Booth: W04


Günther Spelsberg GmbH & Co.KG


Topic: Quickly installed, safe charging - with the new Spelsberg Wallbox!


Tasks: 1. Connecting the charging cable to the wallbox

2. Configuration and commissioning of the Spelsberg Wallbox with the Spelsberg Wallbox app


Stand: W40



Hager Vertriebsgesellschaft mbH & Co. KG


Topic: Get to know Hager products and their safe and easy installation


Tasks: 1. Equipping and wiring a technical center according to the current application rules. 2. Installation of a changeover switch (with Berker W.1 IP55 and Berker Q.7) 3. Wiring and connecting Tehalit device sockets in tehalit BR65 and tehalit BRN65 4. Configuration of a building control system with domovea 5. Installation of an Elcom 2-wire video system for a two-family house

6. Fast and easy planning, from room book to small distribution board, with Hager Ready


Performance level: 1st-4th year of apprenticeship


Stand: W56 & W58


Gustav Hensel GmbH & Co. KG


Topic: Conductor cross-section determination with software tool


Task: Determination of cross-section taking into account the type of installation, disconnection conditions and voltage drop Selection of the appropriate cable junction box for the determined conductor cross-section


Performance level: 1st-3rd year of apprenticeship


Stand: W14



HellermannTyton GmbH


Topic: Cable entry VarioPlate corrugated pipes and holders

Cable Pulling Aid Cable Scout


Tasks: Assemble a frame of the VarioPlate cable entry system Print labels TT431 Insulation tape 1000 --> Tapes for testing (comparison test) (conventional/special) Lay corrugated pipes on the wall and pull cable pulling aid through corrugated pipes


Performance level: 1st year of apprenticeship


Stand: W20


KAISER GmbH & Co. KG


Topic: The basis of good electrical installation


Tasks: Assembly of innovative KAISER products in electrical installation as well as in the area of connectivity and cable glands


Stand: W06


LEDVANCE GmbH


Topic & Tasks: Rewiring lights to use LED tubes


Stand: W32



Lightcycle Retourlogistik und Service GmbH


Topic: Proper disposal and recycling of old lamps and lights Task: Sort waste into the right containers with the interactive game “Recyclingmaster”


Performance level: 1st year of apprenticeship


Stand: W22




MENNEKES Elektrotechnik GmbH & Co. KG


Topic & Task: Connecting a PowerTOP® XTRA coupling


Performance level: 1st year of apprenticeship


Stand: W10



METREL GmbH


Subject: VDE 0100 EVSE

Task: 1. You are checking a house installation. In a socket circuit, you determine the insulation resistance of 0.75 MΩ. a) OK b) not OK

2. You check the installation and measure a symmetrical load on the phase conductors. How high is the current in the neutral conductor?

3. You measure a voltage of 73V between the neutral conductor and PE on a Schuko socket. What could be the cause of this?


Performance level: 3rd year of apprenticeship


Stand: W12


OBO Bettermann Vertrieb Deutschland GmbH & Co. KG


Topic: Industrial installation, building installation and the myOBO app


Tasks:

Industrial installation: Airtight flush-mounted boxes from the WIN series

In front of you you see a plate with installation openings and slots for cable routing. Use our flush-mounted boxes to create an airtight and thermal bridge-free electrical installation over the entire length of the plate. To do this, select the appropriate flush-mounted box variants from the box next to you.

Building installation: Underfloor complete unit UD Home2

In front of you you see an unequipped UD Home2 complete underfloor unit. First equip the UD Home2 with the carrier plate and then wire the 2-way socket in the UD Home2. Then finish the installation by placing the cover on the UD Home2

The myOBO app is here! The mobile device for electrical installation

With the myOBO app, you have access to the OBO product catalogs anytime, anywhere - even offline, without the Internet. You can create and manage projects, export them, and transfer your desired products directly to the shopping cart of the wholesaler of your choice. The myOBO app is also your direct line to OBO customer service: you can contact us by message or direct call if you need help or have questions. This is how you plan and work smartly! - Let our employees explain the myOBO app to you.


Stand: W60



Rutec Licht GmbH & Co. KG


Topic: Practical tips: LED connector technology & troubleshooting)


Task: 1. LED connector technology: feeders, direct connectors

2. Troubleshooting an RGBwLED strip

3. Soldering technique: Making a 2-pole feed


Performance level: 1st-2nd year of apprenticeship


Stand: W16



Safetytest GmbH


Topic: Testing of electrical work equipment according to DIN EN 50699 (DIN VDE 0702)


Task: Standard-compliant testing of various work equipment, evaluation of test results, documentation


Stand: W38



Schneider Electric GmbH


Thema:  1. Wiser 2. ABN 3. QuickFlex


Overview: 1. From switch to standard electronics to smart home

2. Planning of a multi-family house complex including media and distribution panel

3. Easily connect switches and sockets and test them conveniently with intelligent additional functions


Performance level: 1st-3rd year of apprenticeship


Stand: W08


Siedle S.Siedle & Söhne


Topic: Installation / commissioning of Siedle IP system


Task: Installation and commissioning of digital house telephones and connection with the Siedle app


Stand: W36



Trilux Vertrieb GmbH


Thema: SPEED OF LIGHT


Task: Conversion of conventional lighting to LED in a timed competition


Performance level: 1st year of apprenticeship


Stand: W30


WAGO GmbH & Co. Ltd. KG


Topic: Screwless connection technology for connecting electrical wires and cables


Task: Wiring of a switch-on/off switch, installation floor terminals in the small distribution board, switching off with Winsta-Linect


Performance level: 1st-3rd year of apprenticeship


Stand: W52 & W54


Share by: